The ongoing Henley Street Bridge project made some strides this week, according to Tennessee Department of Transportation Officials.
On the south end, the deck steel placement for Span #6 is complete, according to the most recent TDOT update. Deck pour is currently set for the last week in March
On the river, deck panel placement for Span #5 has begun. Pier #5 reconstruction prep work is also being finished. Span #4 caps have been completed. Span #3 column construction and arch repairs continue.
On the north end, Span #1 deck steel placement is nearly complete with deck pour forthcoming.