All dates are subject to change, based on weather conditions and other factors. Currently, the county is approaching the end of its fiscal year, and most projects are repair work instead of new construction.
 
Bridge Work
Rocky Flats Road (near Cosby): Two bridge projects have begun on the two structures, which are about one half mile apart. One bridge is now detoured and the other is open for traffic. No completion time is available.
 
Resurfacing
Knob Creek Road (off of Highway 411): This project is currently 75% complete, with all paving done and striping yet to be finished, and is estimated to be finalized on or around July 8th.

Clear Fork Road: This project is currently about 75% complete. Estimated date of completion is currently unknown.

Beech Branch Subdivision: Resurfacing is complete but restriping is yet to be done. It scheduled for completion on or around July 8.

Union Valley/Raised Gap
Both these roads are complete and striping is finished, with no delays to traffic. 